Pengaruh Keterlambatan Distribusi Material terhadap Waktu dan Biaya, Studi Kasus: Pekerjaan Peningkatan Kawasan Jl. Manunggal Jaya Jalan Poros Provinsi Kampung Kayu Indah (HTI) PT. Wana Kaltim Lestari di Kabupaten Berau
DOI:
https://doi.org/10.55681/sentri.v5i9.7087Keywords:
distribution, productivity, project-cost, implementation-time, road-projectAbstract
Construction projects often encounter challenges that influence schedule, cost, and quality performance. One significant issue is material distribution delay, which may occur due to logistical problems, supplier dependency, and inadequate material management. Such delays can reduce productivity, extend project duration, and increase costs because of additional resource utilization. This study aims to analyze the impact of material distribution delays on time and cost performance in the Road Area Improvement Project of Jl. Manunggal Jaya Provincial Road Section Kampung Kayu Indah (HTI) by PT. Wana Kaltim Lestari in Berau Regency. The research method involved primary and secondary data collection, including work volume, material requirements, project schedules, and implementation data. Analysis was conducted by identifying dominant materials, calculating requirements, and simulating the effect of distribution delays on effective working hours. The results show that delays in material distribution decrease effective working hours, reducing labor and equipment productivity. Consequently, daily work output decreases and project completion becomes longer than planned. Significant delays may extend project duration up to 90 days and increase costs due to prolonged resource use. Effective material distribution management is therefore essential to maintain project performance and minimize delay risks through proper planning, monitoring, and control systems during construction activities.
Downloads
References
Prayitno, Eko. “Analisis Penyebab Keterlambatan Pelaksanaan Proyek Konstruksi Jalan di Kabupaten Kebumen (Studi Kasus Jalan Lingkar Utara Kabupaten Kebumen).” Universitas Islam Indonesia, 2020.
Bagonza, Jimmy Kinyonyi. “Building Information Modelling (BIM) and Internet of Things (IoT) for Enhanced Collaboration and Real-Time Monitoring.” World Journal of Advanced Research and Reviews 27, no. 1 (2025): 2444–2450. https://doi.org/10.30574/wjarr.2025.27.1.2657.
Pradana, T. C. “Analisa Keterlambatan Pekerjaan yang Berdampak Waktu, Biaya dan Mutu pada Pelaksanaan Proyek di Dinas Penataan Ruang Kota Semarang.” 2019.
Putri, I. Ni Luh Putu Cinta Andina, and Sukirno. “Pengaruh Proses Embarkasi dan Debarkasi terhadap Waktu Keterlambatan KM. Dorolonda.” 11 (2026).
Agritama, T. S. R. Randy Putra, and Miftahul Huda. “Faktor-Faktor yang Mempengaruhi Keterlambatan Proyek Konstruksi di Surabaya.” 2, no. 1 (2018): 306–312.
Febriantoro, M. B., S. Susanto, and E. Siswanto. “Nilai Hasil (Earned Value Method).” JURMATEKS: Jurnal Manajemen Teknologi dan Teknik Sipil 5 (2022).
Kharina, F. N., and K. A. Sambowo. “Analisis Keterlambatan Proyek serta Dampaknya terhadap Biaya dan Waktu Pelaksanaan Proyek (Studi Kasus: Proyek Pembangunan Cinere Terrace Suites Apartemen & Citywalk, Jakarta).” Jurnal Infras 5, no. 1 (2019): 13–19.
Jamal, M. R. I. “Analisis Faktor Penyebab Keterlambatan Proyek Konstruksi di Indonesia.” 10, no. 1 (2025): 1–8.
Asmaroni, D. “Analisa Keterlambatan Waktu Pelaksanaan Proyek Pembangunan Gedung Pemerintah di Kabupaten Pamekasan.” 1, no. 1 (2016): 19–23.
Ophiyandi, T., R. A. Hadiguna, and D. E. A. Honesti. “Penyebab Keterlambatan Konstruksi.” 1, no. 2 (2023): 109–114.
Irwan, I., M. Ardan, N. M. Rangkuti, and F. Monalisa. “Analisis Keterlambatan Proyek Konstruksi di PT. PLN (Persero) UIP Sumbagut.” Journal of Civil Engineering, Building and Transportation 6, no. 1 (2022): 20–29. https://doi.org/10.31289/jcebt.v6i1.6817.
Purba, I. Y., and R. W. Dary. “Analisis Risiko terhadap Biaya, Mutu dan Waktu pada Proyek Pembangunan Rumah Susun Kota Tanjung Balai Provinsi Sumatera Utara.” Jurnal Rekayasa Konstruksi dan Teknik Sipil (Agregat) 1, no. 2 (2021). https://doi.org/10.51510/agregat.v1i2.519.
Pondaag, N. E., G. Y. Malingkas, and J. B. Mangare. “Analisis Penyebab Keterlambatan Waktu Pelaksanaan Proyek pada Perumahan Grand Victorian Kairagi.” Jurnal Sipil Statik 8, no. 4 (2020).
Romadhon, A. F., and A. T. Tenriajeng. “Analisis Faktor-Faktor Penyebab Keterlambatan Kerja pada Proyek Pembangunan Gedung Bertingkat di Indonesia.” Jurnal Proyek Teknik Sipil 3, no. 1 (2020): 18–27. https://doi.org/10.14710/potensi.2020.7023.
Syammaun, T., H. A. Rani, J. Amin, and Safriadi. “Pengaruh Keterlambatan Pembangunan Proyek Konstruksi Akibat Pandemi Covid-19.” Siklus: Jurnal Teknik Sipil 9, no. 1 (2023). https://doi.org/10.31849/siklus.v9i1.11833.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Edwin Rifa’i, Moh Abduh

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.