Analisis Dampak Keterlambatan Distribusi Material terhadap Waktu dan Biaya pada Proyek Pembangunan Jalan Kasai–Semanting Kabupaten Berau
DOI:
https://doi.org/10.55681/sentri.v5i9.7080Keywords:
material distribution, productivity, project cost, construction duration, road projectAbstract
Material distribution is one of the important factors affecting the successful implementation of road construction projects. Delays in material distribution can disrupt construction activities, reduce the productivity of labor and equipment, and potentially increase project costs and completion time. This study aims to analyze the impact of material distribution delays on time and cost performance in the Kasai–Semanting Road Construction Project, Berau Regency. The research method was conducted through the collection of primary and secondary data, including work volume data, material requirements, construction schedules, and project implementation data. The analysis was carried out by identifying the dominant materials used in the project, calculating material requirements, and simulating the effect of material distribution delays on effective daily working hours. The results indicate that delays in material distribution cause a reduction in effective working hours, which directly affects labor and equipment productivity, resulting in decreased daily work output and longer project completion time compared to the initial schedule. Material distribution delays also have the potential to increase project costs due to extended resource utilization duration and reduced construction efficiency. Under significant delay conditions, the project completion duration may experience delays of up to 90 days beyond the planned schedule. Based on the findings, it can be concluded that effective material distribution management plays an important role in maintaining project cost and time performance. Therefore, proper material planning, distribution management, and adequate monitoring systems are required to minimize the risk of construction project delays.
Downloads
References
A. T. Gurmu, “Tools for Measuring Construction Materials Management Practices and Predicting Labor Productivity in Multistory Building Projects,” Journal of Construction Engineering and Management, vol. 145, no. 2, pp. 1–12, 2019, doi: 10.1061/(ASCE)CO.1943-7862.0001611.
S. A. Al-Hajj and H. S. Hamani, “Material Management in Construction Projects: Supply Chain Practices and Project Performance,” International Journal of Construction Management, vol. 20, no. 5, pp. 1–12, 2020, doi: 10.1080/15623599.2018.1527381.
S. Yildiz, “Determination of the Importance of Material Management Activities in Construction Works in Terms of Their Contribution to Productivity,” Building Engineering, 2024, doi: 10.59400/be1651.
P. Azzahra and R. Respati, “Analisa Pengaruh Manajemen Material Terhadap Produktivitas Kerja Pada Proyek Konstruksi Gedung Bertingkat di Kota Palangka Raya,” Media Ilmiah Teknik Sipil, vol. 12, no. 2, pp. 159–166, 2024, doi: 10.33084/mits.v12i2.7323.
S. Awaad, D. M. Mansour, I. Mahdi, and I. Abdelrasheed, “Impact of Material Supply Chain on the Productivity Optimization for the Construction of Roads Projects,” Scientific Reports, vol. 14, 2024, doi: 10.1038/s41598-024-53660-6.
H. L. Y. Ting, S. H. H. Osman, and M. A. A. Rahman, “Factors Affecting Construction Productivity Performance: A Review,” International Journal of Construction Management, 2021, doi: 10.1080/15623599.2021.1883315.
M. R. Islam, M. H. Rahman, and M. A. Hossain, “Evaluation of Construction Supply Chain Management Practices and Their Impact on Project Performance,” Journal of Construction Engineering and Management, 2021.
N. El-Sayegh, “Construction Project Delays and Cost Overruns: Causes and Effects,” International Journal of Project Management, 2018.
A. Ashar, M. N. Abduh, and E. Yuniarto, “Pengaruh Manajemen Material Terhadap Produktivitas Kerja Pada Pekerjaan Pembangunan Mall Pelayanan Publik Gowa,” Jurnal Penelitian Teknik Sipil Konsolidasi, 2024.
Data Proyek Pembangunan Jalan Kasai–Semanting Kabupaten Berau, Dokumen Rencana Anggaran Biaya, Jadwal Pelaksanaan, dan Data Kebutuhan Material Proyek, 2024.
I. Soeharto, Manajemen Proyek: Dari Konseptual Sampai Operasional. Jakarta, Indonesia: Erlangga, 1999.
A. Husen, Manajemen Proyek. Yogyakarta, Indonesia: Andi Offset, 2011.
W. I. Ervianto, Manajemen Proyek Konstruksi. Yogyakarta, Indonesia: Andi, 2005.
D. S. Barrie and B. C. Paulson, Professional Construction Management. New York, NY, USA: McGraw-Hill, 1992.
R. H. Clough, G. A. Sears, and S. K. Sears, Construction Project Management. New Jersey, NJ, USA: John Wiley & Sons, 2008.
W. J. O’Brien, C. T. Formoso, R. Vrijhoef, and K. London, Construction Supply Chain Management Handbook. Boca Raton, FL, USA: CRC Press, 2008.
M. Sambasivan and Y. W. Soon, “Causes and Effects of Delays in Malaysian Construction Industry,” International Journal of Project Management, vol. 25, no. 5, pp. 517–526, 2007.
H. Doloi, A. Sawhney, K. C. Iyer, and S. Rentala, “Analysing Factors Affecting Delays in Indian Construction Projects,” International Journal of Project Management, vol. 30, no. 4, pp. 479–489, 2012.
Project Management Institute (PMI), A Guide to the Project Management Body of Knowledge (PMBOK Guide), 7th ed. Pennsylvania, USA: Project Management Institute, 2021.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Bambang Edy Maryono, Andi Syaiful Amal

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.