Efektivitas Kontrak Lump Sum pada Proyek Konstruksi di Kabupaten Kutai Barat

Authors

  • Sopiani Sopiani Universitas 17 Agustus 1945 Samarinda
  • Findia Findia Universitas 17 Agustus 1945 Samarinda
  • Habir Habir Universitas 17 Agustus 1945 Samarinda

DOI:

https://doi.org/10.55681/sentri.v5i1.5457

Keywords:

Lump sum contracts, construction management, cost control, project effectiveness, risk management

Abstract

Lump sum contracts are widely used in Indonesian construction, yet questions persist about which factors—cost effectiveness, schedule effectiveness, or risk management—most significantly influence work quality and contractor satisfaction. This research addresses two critical questions: (1) what factors affect lump sum contract effectiveness based on project performance, and (2) which of the three variables most significantly impact work quality and contractor satisfaction in West Kutai District projects. The study employed quantitative methods with 30 contractor respondents, collecting data through structured 5-point Likert scale questionnaires. Validity was tested using Pearson correlation analysis and reliability assessed via Cronbach's Alpha. Multiple linear regression examined the influence of the three independent variables on work quality and contractor satisfaction. Results indicate that cost effectiveness significantly affects contractor satisfaction (β = 0.337; t = 2.097; p = 0.046), while schedule effectiveness and risk management show no significant effects on either dependent variable. The regression models explain only 41.6% of contractor satisfaction variance and 22.4% of work quality variance, indicating substantial unexplained factors. These findings demonstrate that among examined variables, cost effectiveness is the primary determinant of contractor satisfaction in lump sum contracts. However, the incomplete variance explanation emphasizes that identifying additional factors influencing contract effectiveness is essential for improving construction project outcomes in regional contexts

Downloads

Download data is not yet available.

References

Lam, K. C., Wang, D., & Lee, P. K. "Risks Associated with Allowable Cost-Plus-Fee Contracts." Journal of Construction Engineering and Management, Vol. 133, No. 6 (2007), pp. 454-463.

Chen, Z., & Ping, H. "Effects of Uncertainty on Allocation of Risk in Public-Private Partnership Projects." Journal of Construction Engineering and Management, Vol. 138, No. 2 (2012), pp. 174-185.

Widiastuty, H., Mukti, R., & Setyanto, B. "Aplikasi Kontrak Harga Tetap dalam Proyek Konstruksi di Indonesia: Studi Kasus Proyek Infrastruktur Regional." Jurnal Teknik Sipil, Vol. 24, No. 3 (2017), pp. 215-228.

Mohamad, Z., Ibrahim, R., & Ahmad, M. N. "Lump Sum Contract as an Alternative Procurement Method: Characteristics and Implementation." Construction Management and Economics, Vol. 25, No. 7 (2007), pp. 691-706.

Rienecker, L., & Stray Jørgensen, P. The Good Project: A Handbook for Sensible Project Work. Copenhagen: Samfundslitteratur Press (2005).

Semple, C., Hartman, F. T., & Jergeas, G. F. "Construction Claims and Disputes: Causes and Cost/Time Overruns." Journal of Construction Engineering and Management, Vol. 120, No. 4 (1994), pp. 785-795.

Arditi, D., Akan, G. T., & Gurdamar, S. "Reasons for Delays in Public Projects in Turkey." Construction Management and Economics, Vol. 3, No. 2 (1985), pp. 171-181.

Enshassi, A., Muhammad, S., & Abushaban, S. "Factors Affecting the Performance of Construction Projects in the Gaza Strip." Journal of Civil Engineering and Management, Vol. 15, No. 3 (2009), pp. 269-280.

Kometa, S. T., Olomolaiye, P. O., & Harris, F. C. "Attributes of UK Construction Clients' Influencing Project Performance." Construction Management and Economics, Vol. 12, No. 5 (1994), pp. 433-443.

Peraturan Pemerintah Nomor 29 Tahun 2000 tentang Penyelenggaraan Jasa Konstruksi, Pasal 1, No. 29. Jakarta: Menteri Pekerjaan Umum (2000).

Undang-Undang Nomor 2 Tahun 2017 tentang Jasa Konstruksi, Pasal 1-5, No. 2. Jakarta: Presiden Republik Indonesia (2017).

Direktorat Jenderal Bina Marga. "Standar Operasional Prosedur Penetapan Kontrak Lump Sum Jasa Konsultansi SOP/UPM/DJBM-70 Rev:01." Jakarta: Kementerian Pekerjaan Umum (2015).

Cheung, S. O., Ng, T. S., Wong, S. P., & Suen, H. C. "Behavioral Aspects in Construction Partnering." International Journal of Project Management, Vol. 21, No. 5 (2003), pp. 333-343.

Walker, D., & Stephens, J. "Measurement of Felt Risk in Construction Projects." International Journal of Project Management, Vol. 14, No. 4 (1996), pp. 221-224.

Turner, J. R., & Cochrane, R. A. "Goals-and-Methods Matrix: Coping with Projects with Ill Defined Goals and/or Methods of Achieving Them." International Journal of Project Management, Vol. 11, No. 2 (1993), pp. 93-102.

Flyvbjerg, B., Holm, M. K. S., & Buhl, S. L. "What Causes Cost Overrun in Transport Infrastructure Projects?" Transport Reviews, Vol. 24, No. 1 (2004), pp. 3-18.

Larson, E. W., & Gobeli, D. H. "Significance of Project Management Structure on Development Success." IEEE Transactions on Engineering Management, Vol. 36, No. 2 (1989), pp. 119-125.

Merrow, E. W. "Understanding the Lessons of Project Failure." RAND Journal, Vol. 39, No. 4 (2011), pp. 154-167.

Davis, K. "An Empirical Investigation of Collaborative Characteristics and Project Success: What We Know, and What We Need to Learn." IEEE Transactions on Engineering Management, Vol. 61, No. 4 (2014), pp. 625-634.

Atkinson, R. "Project Management: Cost, Time and Quality, Two Best Guesses and a Phenomenon, Its Time to Accept Other Success Criteria." International Journal of Project Management, Vol. 17, No. 6 (1999), pp. 337-342.

Baccarini, D. "The Logical Framework Method for Defining Project Success." Project Management Journal, Vol. 30, No. 4 (1999), pp. 25-32.

Navarre, C., & Schaan, J. L. "Design of Project-Oriented Organizations." Journal of Business Research, Vol. 18, No. 3 (1990), pp. 211-226.

Al-Momani, A. H. "Construction Delay: A Quantitative Analysis." International Journal of Project Management, Vol. 18, No. 1 (2000), pp. 51-59.

Thakur, G. S. "Factors Affecting Delays in Indian Construction Projects." IOSR Journal of Mechanical and Civil Engineering, Vol. 8, No. 2 (2013), pp. 65-73.

Odeyinka, H. A., & Yusif, A. "The Causes and Effects of Construction Delays on Completion Cost of Housing Project." Journal of Financial Management of Property and Construction, Vol. 3, No. 1 (1997), pp. 31-44.

Chapman, R. J. "The Effectiveness of Working Group Risk Identification and Assessment Techniques." International Journal of Project Management, Vol. 16, No. 6 (1998), pp. 333-343.

Sambasivan, M., & Soon, Y. W. "Causes and Effects of Delays in Malaysian Construction Industry." International Journal of Project Management, Vol. 25, No. 5 (2007), pp. 517-526.

Hwang, B. G., Zhao, X., & Toh, S. L. "Risk Management in Small Construction Projects in Singapore: Status, Barriers and Recommendations." International Journal of Project Management, Vol. 32, No. 1 (2014), pp. 116-124.

Mohan, S., & Gopalakrishnan, K. "A Framework for Quality Management in Construction Industry." Construction Management and Economics, Vol. 23, No. 8 (2005), pp. 853-864.

Crosby, P. B. Quality Is Free: The Art of Making Quality Certain. New York: McGraw-Hill (1979).

Williams, T. M., & Samset, K. "Issues in Managing Uncertainty and Risk in Tunnels Projects." International Journal of Project Management, Vol. 28, No. 2 (2010), pp. 125-134.

Tabachnick, B. G., & Fidell, L. S. Using Multivariate Statistics (6th ed.). Boston: Pearson Education (2013).

Taber, K. S. "The Use of Cronbach's Alpha When Developing and Reporting Research Instruments in Science Education." Research in Science Education, Vol. 48, No. 6 (2018), pp. 1273-1296.

Downloads

Published

2026-01-31

How to Cite

Sopiani, S., Findia, F., & Habir, H. (2026). Efektivitas Kontrak Lump Sum pada Proyek Konstruksi di Kabupaten Kutai Barat. SENTRI: Jurnal Riset Ilmiah, 5(1), 480–490. https://doi.org/10.55681/sentri.v5i1.5457