Analisis Metode Pelaksanaan dan Kinerja Struktur Gedung Parkir Bertingkat Menggunakan Sistem Precast dan Minipile

Studi Kasus Plaza 6 Pondok Indah

Authors

  • Edison Hatoguan Manurung Universitas Mpu Tantular
  • Sri Hartanto Universitas Mpu Tantular

DOI:

https://doi.org/10.55681/sentri.v4i7.4199

Keywords:

multi-story parking, minipile, steel structure, precast, on-site method, project efficiency

Abstract

The construction of a multi-story parking building in densely populated areas such as Plaza 6 Pondok Indah is a response to limited land availability and the increasing demand for parking facilities. This project employs modern construction methods, such as minipile foundations and precast structural systems, to accelerate project timelines and maintain on-site efficiency. This study aims to directly examine the implementation process and structural systems used on-site, as well as evaluate their effectiveness in terms of technical performance and construction time. Data were collected through direct observation at the project site, technical documentation, and informal discussions with project personnel. Emphasis was placed on the stages of foundation work, substructure components such as pile caps and tie beams, and the installation of precast components on each floor. Additionally, the installation of steel structures was an essential aspect of this study. Observations revealed that the use of precast floor slabs significantly reduced construction time by minimizing the need for formwork and scaffolding. The steel frame system provided advantages in installation flexibility and faster on-site mobilization. The selection of minipiles as the foundation type was also appropriate for the limited land space and moderate soil bearing capacity. Overall, the construction methods used in this project offered substantial benefits in terms of time and on-site efficiency. This study may serve as an initial reference for similar projects, particularly in utilizing a combination of steel structures, precast elements, and deep foundations.

Downloads

Download data is not yet available.

References

Andri Dwi Laksono, Fatmawati, E., & Widhiarto, H. (2023). Perencanaan ulang pondasi tiang pancang mini pile (square pile) sebagai alternatif perkuatan pondasi pada proyek pembangunan SMPN 9 Kota Kediri. Jurnal Teknik Sipil, 8(2), 8–19. https://doi.org/10.56071/deteksi.v8i2.583

Bahariansyah, M. A. N., Krisnamurti, K., & Kriswardhana, W. (2021). Perencanaan gedung parkir bertingkat terpusat Universitas Jember. Jurnal Ilmiah MITSU, 9(1), 57–64. https://doi.org/10.24929/ft.v9i1.993

Bahauddin, M., Syahrial, & Rangkuti, M. A. (2021). Metode Pelaksanaan Proyek Konstruksi Gedung Bertingkat. Medan: USU Press.

Fernando, F., & Dompak, T. (2014). Analisis Perbandingan Infrastruktur Transportasi Di Negara Indonesia Dan Jepang. 288–292

Gazali, A., Rachman, T. A., & Purnamasari, E. (2023). Analisis efisiensi daya dukung pondasi mini pile dari aspek faktor keamanan. Prosiding SNITT Politeknik Negeri Balikpapan, 1, 55–61.

Hartawan, I. G. A., Wibawa, I. M. S., & Wirawan, P. (2024). Rancangan struktur gedung parkir bertingkat dengan material beton bertulang menggunakan program SAP2000. Jurnal Teknik Sipil, 4(1), 19–22.

Kementerian PUPR. (2021). SNI 2847:2021 – Tata cara perencanaan struktur beton untuk bangunan gedung. Jakarta: Badan Standardisasi Nasional.

Kementerian PUPR. (2022). SNI 1726:2022 – Tata cara perencanaan ketahanan gempa untuk struktur gedung dan non-gedung. Jakarta: BSN.

Li, J., Zhang, X., & Wang, T. (2020). "Impact of Modern Construction Technologies on Infrastructure Project Efficiency." International Journal of Construction Engineering and Management.

Sekaryadi, Y., & Hermawan, A. (2020). Evaluasi pelat lantai pracetak dibandingkan pelat konvensional pada Gedung Rusunawa Sukabumi. Jurnal Momen Teknik Sipil, 3(1), 49. https://doi.org/10.35194/momen.v3i1.1022

Singh, A., & Jain, P. (2019). "Relevance of Traditional Construction Methods in Developing Regions." Journal of Civil Engineering and Technology.

Siswanto, S., & Prijasambada, P. (2022). Analisis kinerja struktur gedung bertingkat dengan metode pushover. IKRAITH-Teknologi, 7(1), 46–52. https://doi.org/10.37817/ikraith-teknologi.v7i1.2319

Syamsuddin, J., Warastuti, N., & Arini, R. N. (2019). Perbandingan biaya dan waktu pelat pracetak dan konvensional di proyek dermaga. Jurnal Infrastruktur, 4(2), 127–134. https://doi.org/10.35814/infrastruktur.v4i2.702

Tjahjono, R., & Triwinarto, J. (2004). Tipologi Konstruksi Tradisional pada Cungkup Makam Prapen. Journal Ruas, 2(1), 16–25.

Trave, J. (2023). Evaluasi aspek keselamatan pada gedung parkir bertingkat di Depok Town Square. Jurnal Teknik Sipil, 27(1), 57–64.

Wibowo, A. (2018). Teknik Konstruksi Bangunan Gedung Tinggi. Yogyakarta: Graha Ilmu.

Wijaya, D., & Prasetyo, A. (2020). Efisiensi metode pracetak dalam pembangunan struktur atas gedung bertingkat. Jurnal Konstruksi, 6(1), 33–40.

Yulianto, B., & Sunaryo, R. (2021). Implementasi struktur baja dalam pembangunan gedung parkir pusat kota. Jurnal Rekayasa Sipil dan Arsitektur, 5(2), 12–19.

Downloads

Published

2025-07-30

How to Cite

Manurung, E. H., & Hartanto, S. (2025). Analisis Metode Pelaksanaan dan Kinerja Struktur Gedung Parkir Bertingkat Menggunakan Sistem Precast dan Minipile: Studi Kasus Plaza 6 Pondok Indah. SENTRI: Jurnal Riset Ilmiah, 4(7), 656–663. https://doi.org/10.55681/sentri.v4i7.4199