Evaluating the Effectiveness of Construction Management on Quality, Time, Cost, and Risk Performance in the Nuclear Medicine Building Project at Dr. Soedarso Regional General Hospital, Pontianak

Authors

  • Iin Arianti Department of Civil Engineering, Politeknik Negeri Pontianak
  • Sarah Safira Department of Civil Engineering, Politeknik Negeri Pontianak
  • Salwa Putri Nabilla Department of Civil Engineering, Politeknik Negeri Pontianak
  • Muhammad Rafani Department of Civil Engineering, Politeknik Negeri Pontianak
  • Nurul Fitriani Department of Civil Engineering, Politeknik Negeri Pontianak
  • Wattini Wattini Department of Civil Engineering, Politeknik Negeri Pontianak
  • Agus Eko Tejo Sasongko Department of Business Administration, Politeknik Negeri Pontianak

DOI:

https://doi.org/10.55681/sentri.v4i12.5073

Keywords:

Construction Management, Implementation, Costs, Time, Human Resources, Quality

Abstract

The Nuclear Medicine Building is a strategic healthcare facility that utilizes open radiation sources for diagnosis and treatment. Due to its high structural complexity and radiological risks, this study aims to analyze the construction management implementation of the Nuclear Medicine Building project at Dr. Soedarso Regional General Hospital, Pontianak. The research utilizes primary data from field observations and secondary data from project documents, analyzed through four critical aspects: cost, time, quality, and human resources. The study produces an Implementation Budget Plan (RAP) totaling IDR 7,904,689,106.53. Time management planning establishes a project duration of 15 weeks or 108 calendar days, utilizing Network Planning and Bar Charts to monitor the critical path. Quality management is implemented through a quality control table to ensure technical specification compliance, while human resource planning identifies a peak labor requirement of 100 workers per day during the 7th week. Analytically, the integration of cost and time in this project validates the "Iron Triangle" theory, where precision in substructure work (foundations) serves as the primary determinant of schedule success due to the specialized loading requirements of nuclear facilities. These findings suggest that for specialized medical infrastructure, radiation safety standards demand more stringent productivity coefficients compared to general building projects. The academic implication of this research indicates that the application of national AHSP regulations (PUPR No. 8 of 2023) requires adjustment for site-specific risk variables in high-hazard buildings to prevent deviations between technical planning and field reality. These results contribute to the project management literature on the necessity of integrated frameworks in enhancing the resilience of regional medical referral infrastructure.

Downloads

Download data is not yet available.

References

Bangash, M. Y. H. (2011). Structures for Nuclear Facilities: Analysis, Design, and Construction. Springer-Verlag. https://doi.org/10.1007/978-3-642-12560-7

Ervianto, W. I. (2023). Construction Project Management. Publisher: Andi

Yakub, Abidin, & Biharudin. (2021). Management Project. Publisner: Campustaka.

Project Management Institute. (2017). A guide to the project management body of knowledge (PMBOK® Guide) (6th ed.). Pennsylvania, USA: Project Management Institute.

Mulyono, A. T. (2012). Construction project quality management. Bandung: Publisher: ITB.

Afiya, D. N., Rahmawati, S., & Sari, R. (2023). Time management analysis in construction projects using network planning method. Jurnal Teknik Sipil Nusantara, 12(2), 45–53.

Rani, A. (2016). Construction project management. Deepublish.

Project Management Institute. (2018). A guide to the project management body of knowledge (PMBOK® Guide) (7th ed.). Project Management Institute.

Kerzner, H. (2017). Project management: A systems approach to planning, scheduling, and controlling (12th ed.). John Wiley & Sons.

Pitaloka, D., Nurhadi, A., & Fadillah, M. (n.d.). Analysis of the preparation of implementation budget plan (RAP) based on actual market prices. Universitas Negeri Semarang.

Afiya, N., et al. (2023). Application of time management in construction projects. International Journal of Civil Engineering and Technology.

Angellia, F., Rahayu, P. W., Suryaatmaja, K., Utami, R., Muslimim, M., Iswahyudi, M. S., Setiawan, I., Arsana, I. N. A., Nasirly, R., & Purbaratri, W. (2023). Textbook of information systems project management (Efitra, Ed.; 1st ed.). PT Sonpedia Publishing Indonesia.

Ramadhan, P. M., & Anwar, S. (2022). Construction management analysis on Cikeusal Bridge. Jurnal Konstruksi dan Infrastruktur, 10(1), 1–6. https://doi.org/10.33603/jki.v10i1.6586

Kusumo, E., & Hakim, F. F. (2023). Construction management textbook: Scheduling for beginners using ProjectLibre application (T. Azhari, Ed.). Deepublish Digital,

Surbakti, M. (2013). Quality control in building construction projects. Jurnal Teknik Sipil Universitas Sumatera Utara, 8(1), 12–18.

Astri, D. (2022). Human resource management in the implementation of construction projects. Jurnal Teknik Sipil dan Arsitektur, 10(3), 101–108.

Syahbani, G., Fadli, H., Utomo, S., Reski, I. A., & others. (2022). Construction management in advanced implementation of indoor stadium building, Landak Regency, West Kalimantan. Journal of Civil Engineering and Technology, 2(2), 2775–0655.

Ministry of Public Works and Housing (PUPR). (2023). Regulation of the Minister of Public Works and Housing No. 8 of 2023 concerning guidelines for unit price analysis in public works. Ministry of Public Works and Housing.

Listiani, S., & Kamandang, F. (2023). Analysis of labor productivity based on AHSP coefficients in building construction projects. Jurnal Rekayasa Sipil, 14(1), 33–40.

Widiasanti, I., & Lenggogeni, R. (2013). Construction project management. Alfabeta.

Downloads

Published

2025-12-31

How to Cite

Arianti, I., Safira, S., Nabilla, S. P., Rafani, M., Fitriani, N., Wattini, W., & Sasongko, A. E. T. (2025). Evaluating the Effectiveness of Construction Management on Quality, Time, Cost, and Risk Performance in the Nuclear Medicine Building Project at Dr. Soedarso Regional General Hospital, Pontianak. SENTRI: Jurnal Riset Ilmiah, 4(12), 4080–4095. https://doi.org/10.55681/sentri.v4i12.5073